The sample passed incoming inspection on a single piece. Then production started and the next lot behaved differently. First article inspection (FAI) exists to catch this before the lot is built. This page is for quality and procurement teams: what to require on a first article for an RF cable assembly, how to judge the results and how to keep repeat orders identical.
On This Page
A first article inspection confirms that the supplier's process produces an assembly that meets your drawing, before the full lot is built. It is a record of one piece, measured against every requirement, and a reference for all that follow.
It is different from a routine test report, which records results on each production piece. For what a routine report contains, see cable assembly test report contents. The FAI adds the process evidence: what was built, with what, and how it was checked.
| Item | What to check | Why it matters |
|---|---|---|
| Dimensional check | Overall length, strip dimensions and connector orientation against the drawing | Length error is the most common nonconformance |
| Materials used | Cable type and lot, connector part numbers and lots | Confirms the build matches the spec and can be repeated |
| Crimp evidence | Crimp height, pull force or a cross-section of a sacrificial piece | A weak crimp passes a bench test and fails in the field |
| Electrical results | VSWR, insertion loss and continuity over your frequency band | Shows RF performance against your limits |
| Visual and workmanship | Solder or crimp finish, heat shrink, cleanliness, no cable damage | Shows process quality |
| Labelling and marking | Part number, revision, date code | Needed for traceability |
| Packaging | How the piece was protected and shipped | Connectors damaged in transit fail incoming inspection |
Key idea
Ask for the FAI measurements against the drawing numbers, not a "passed" stamp. A stamp tells you someone decided it was fine. Numbers tell you by how much.
Need a first article with measured data before you commit to production?
Request a First ArticleThe FAI approves one piece. Repeat orders stay identical when the supplier records how that piece was built.
Ask any supplier for these during qualification. Our 12-point audit includes the questions.
Ask for an FAI when
You can skip a full FAI when
A middle path for small orders is a first-piece check inside the order: the supplier builds one piece first, sends the measurements and builds the rest after your approval. At SigmaRF every assembly is swept on a VNA for VSWR and insertion loss, so FAI data is the same data we collect on each piece, with the build record added.
Copy this into your purchase order requirements
What is a first article inspection for cable assemblies?
A documented check of the first piece built to your drawing, covering dimensions, materials, crimp quality and electrical results, done before full production.
What should a cable assembly FAI report include?
Drawing revision, dimensions, cable and connector lots, crimp evidence, VSWR and insertion loss data, workmanship check and a written approval.
Is an FAI the same as a test report?
No. A test report records electrical results on production pieces. An FAI also records the build process and materials for the first piece.
Do I need PPAP for cable assemblies?
PPAP is a formal automotive approval process. Whether you need it depends on your industry and customer. For most RF assemblies an FAI plus a build record is the working equivalent. Ask your quality team what your customer requires.
How long does an FAI add to lead time?
It adds the time to build, measure and approve one piece, often a few days. Many buyers approve the first piece while the supplier prepares the rest of the lot.
Can SigmaRF provide first article data?
Yes. Request a first article through the contact page and we will send per-unit measurements with the piece.
How do I keep later lots identical to the first article?
Lock the drawing revision, keep a golden sample, ask for lot traceability and require notice of any process or material change.
A first article turns "it should work" into measured evidence. Require numbers, keep a golden sample, lock the revision and ask the supplier to record the build. Then repeat orders match the piece you approved.